Project Description

The annual Street Resurfacing Program combines publicly bid projects with the City of Fort Wayne's capabilities to mill existing deteriorated asphalt street pavements and then establish a newly restored driving surface. The City of Fort Wayne has a pavement management system (PASER) that rates the condition of all streets within the city limits on a regular and consistent basis. These ratings range from 1 being the worst condition to 10 being the best condition. These ratings are used each year to determine which streets meet the criteria for resurfacing.

After determining all the streets that meet these criteria, the City will look at all conflicting, upcoming construction projects that can range from utility projects to future roadway expansions. These conflicts will be taken into consideration in determining whether to move forward with the resurfacing of those streets. The resurfacing of some streets may be delayed until after other, unrelated work, is completed so newly resurfaced streets are not damaged by this construction.

This construction year we will be resurfacing approximately 15 miles of asphalt pavement including several multi-lane roadways. There are more streets that meet the criteria for resurfacing than funds available. The city will then evaluate the most efficient manner of grouping these streets into resurfacing packages to be bid out to contractors for that current year. Our 2026 Street Resurfacing Program projects are outlined below:

The list of streets scheduled for resurfacing are subject to change due to conflicts with utilities or budget issues. If a street is removed due to a conflict, this street will be added to next year's resurfacing packages.

Note: Street Resurfacing Projects are grouped by proximity and may not follow City quadrant boundaries.

Northeast

The following street segments in Northeast Fort Wayne are expected to be resurfaced as a part of the 2026 Resurfacing Program through Public Works:

Northwest

The following street segments in Northwest Fort Wayne are expected to be resurfaced as a part of the 2026 Resurfacing Program through Public Works:

  • E Cook Rd - Coldwater Rd to Auburn Rd
  • W Ludwig Rd - Lima Rd to Bridge

Southeast

The following street segments in Southeast Fort Wayne are expected to be resurfaced as a part of the 2026 Resurfacing Program through Public Works:

  • Maumee Ave - Chute St east to E Washington Blvd
  • Glasgow Ave - Maumee Ave to E Wayne St
  • E Washington Blvd - Edsall Ave to Kitch St
  • Edsall Ave - Winch St to McDonald St
  • Morningside Dr - Gregory Dr to S Calhoun St
  • Gregory Dr - Cul-de-sac to Cul-de-sac
  • Alverno Dr - Gregory Dr to Casino Dr
  • Rexford Dr - Gregory Dr to Casino Dr
  • Casino Dr - Eton Dr to Rexford R
  • Eton Dr - Corwin Ln to Casino Dr

Southwest

The following street segments in Southwest Fort Wayne are expected to be resurfaced as a part of the 2026 Resurfacing Program through Public Works:

  • Hadley Rd -I-69 to City limits
  • Covington Rd Covington Creek Trl to Getz Rd
  • Bittersweet Moors Dr - Bittersweet Moors Ct to W Jefferson Blvd
  • Bittersweet Moors Ct - Cul-de-sac to Sweet Briar Dr
  • Snowberry Dr - Sweet Briar Dr to Brigadoon Ct
  • Spirea Ct - Cul-de-sac to Snowberry Dr
  • W Sycamore Hills Dr - Bridge to Bridge
  • Smugglers Cv - Oak Borough Run to Cul-de-sac
  • Oak Borough Run - Covington Rd to Oak Glen Trl
  • Oak Glen Trl - Oak Borough Run to Castle Creek Dr
  • Castle Creek Dr - Oak Glen Trl to Copper Hill Run
  • Hialeah Ln - Oak Borough Run to Greenbriar Dr
  • PAY ATTENTION

    AVOID DISTRACTIONS!

    Be aware of all signage and reduced speeds. Avoid distractions such as cell phones, eating/drinking, and radio.

  • BARRICADES

    DO NOT MOVE BARRICADES!

    The contractor will move them once pavement passes testing and can withstand vehicle weights.

  • WORKER SAFETY

    BE PREPARED TO STOP!

    Slow down and give workers extra room. Drive cautiously through the jobsite especially If workers are on site.