City Council Committee Session
Councilmembers discuss the ordinances and resolutions for each committee in depth and vote for a recommendation on each item. No final action is taken. You can find the full agenda here.
Public Works Committee
Chair Councilwoman Michelle Chambers
Ordinance approving Professional Services Agreement for Clinton St Widening, Auburn to Mayhew ROW. This is a Federal Project with INDOT that has a cost sharing of 80/20 with the City. The project is planned in 4 phases (one of these 3 will be funded by the County)
Council District: 2nd District
Department requesting ordinance: Transportation Engineering
Applicant/Vendor: American Structure Point
Total Cost: $654,943.00 NTE
Ordinance approving Construction Contract – Concord Hills Concrete Street Repairs. Applicant was the lowest, most responsive bidder among 4 bidders and was below the Engineer’s estimate for this project.
Council District: 2nd District
Department requesting ordinance: Public Works
Applicant/Vendor: Hipskind Concrete
Total Cost: $466,775.00, Funding Source: LIT-ED
Ordinance approving Construction Contract – 2026 Resurfacing Package Northwest. Applicant was the lowest, most responsive bidder among 3 bidders.
Council District: 2nd/3rd Districts
Department requesting ordinance: Public Works
Applicant/Vendor: Wayne Asphalt and Construction
Total Cost: $879,152.00, Funding Source: MVH
City Utilities Committee
Chair Councilman Russ Jehl
Ordinance approving Field Operations Blanket Purchase Order for Grinder Inventory Parts. This is a sole source commodity purchase
Council District: N/A
Department requesting ordinance: City Utilities, Funding Source:
Applicant/Vendor: American Pump Repair & Service
Total Cost: $330,000.00
Ordinance approving Construction Contracts – CU 2026 On-Call Asphalt Restoration Servies. This is for infrastructure repairs as needed for sewer and water mains.
Council District: N/A
Department requesting ordinance: City Utilities
Applicant/Vendor: Robbco Inc
Total Cost: $800,000, Funding Source: Water, Sewer and Stormwater Revenue
Ordinance approving Purchase of Replacement RAW Wastewater Pump. The original pump was installed in 2004 and reached beyond its useful life, requiring replacement.
Council District: N/A
Department requesting ordinance: City Utilities
Applicant/Vendor: Xylem Water Solutions
Total Cost: $272,713.17, Funding Source: Sewer Utility Revenue
Ordinance approving Construction Contract – CU 2026 Concrete Restoration
Council District: N/A
Department requesting ordinance: City Utilities
Applicant/Vendor: Malott Contracting
Funding Source: $265,160.45, Funding Source: Water, Sewer and Stormwater Revenue
Ordinance approving Construction Contracts – CU 2026 On-Call Concrete Restoration Services. These cuts are made during the repair of CU infrastructure.
Council District: N/A
Department requesting ordinance: City Utilities
Applicant/Vendor: Mallot Contracting, Exterior Service, Pulver Asphalt Paving
Total Cost: NTE $400,000, Funding Source: Water, Sewer and Stormwater
Ordinance approving contribution in aid of construction agreement. I&M is the electric utility provider for CU facilities. I&M infrastructure is being completed to extend necessary 3-phase power to this pumping facility. Improvements are included as a part of the overall Paulding Rd Lift Station project.
Council District: N/A
Department requesting ordinance: City Utilities
Applicant/Vendor: Indiana Michigan Power
Total Cost: $208,447.42, Funding Source: Sewer Utility